Case study: the vessel is cancelled and the goods will miss the L/C shipment date
The goods are ready, but the shipping line postpones the sailing and the L/C's latest shipment date is about to pass. How to handle it without losing money.
This is a composite, illustrative case.
What happened
A garment exporter had an L/C with a latest shipment date at the end of the month. Three days before sailing, the shipping line announced a one-week delay because of a schedule change. On the next sailing, the date on the bill of lading would be later than the L/C allows.
The options
- Find another sailing through the forwarder or another shipping line, even at a higher freight rate.
- Ask the buyer to amend the L/C to extend the shipment and expiry dates. The buyer must ask the issuing bank to amend it, which costs money and time.
- Ship late and present discrepant documents: this depends on the buyer accepting, with the risk of being squeezed on price.
The best way to handle it
- Tell the buyer immediately, explain the cause and propose options.
- Look for an alternative sailing and request an L/C amendment at the same time.
- Keep the shipping line's notice as evidence.
Prevention
- Book early and have a backup forwarder.
- Negotiate L/Cs with a safety margin on the shipment and expiry dates.
- Include a clause in the contract on delays caused by carriers.
- Finish production a few days before the sailing date.