Case study: a sudden anti-dumping duty in the middle of a contract
The importing market announces trade remedy duties while the company has a long-term contract. Who pays the duty and how to respond.
This is a composite, illustrative case.
What happened
A company had a one-year supply contract with an overseas buyer. Partway through, the importing country announced provisional anti-dumping duties on this product from Vietnam. The buyer asked the company to cut its price to cover the duty, or it would cancel the remaining orders.
The problem
- The contract had no clause on new duties.
- The duty is levied on imports and paid by the importer, but the buyer wanted to shift the burden to the seller.
How it was handled
- Check whether the company qualifies for a lower individual duty rate (if it took part in answering the investigation).
- Negotiate cost-sharing and adjust the delivery schedule.
- Consider shifting to other markets.
- Contact the industry association and the trade remedies authority for support.
Lessons
- Long-term contracts should include clauses on changes in duties and policy.
- Follow trade remedy alerts so you can act early.
- When there's an investigation, cooperate fully to obtain an individual rate.
- Diversify markets.