Writing a watertight payment clause in an export contract
When payment is due, in which currency, who pays bank charges and which documents: a clear payment clause gets you paid in full and on time.
In the article on L/Cs and T/T, I covered how to choose a method. This one focuses on writing the payment clause in the contract so there are no loopholes.
What it must contain
- Method: T/T, L/C, D/P or a combination.
- Percentages and timing: for example "30% of the total contract value paid in advance by T/T within 7 days of signing; the remaining 70% paid before the seller releases the original bill of lading or a telex release".
- Currency: USD, EUR or another currency. If payment is made in a currency other than the pricing currency, state the exchange rate that applies.
- Receiving account: bank name, account holder, account number, SWIFT code. Add a sentence: "Any change of bank account is valid only with a signed and stamped letter confirmed by telephone" to guard against bank-detail fraud.
- Bank charges: normally each party pays the charges in its own country. State it clearly so you aren't short-paid because of intermediary bank deductions.
For an L/C, also state
- The type: irrevocable, at sight or usance, confirmed or not.
- The issuing bank must be acceptable to the seller.
- The deadline for opening the L/C: for example "no later than 15 days before the shipment date". If the buyer opens it late, the seller may push back the shipment date accordingly or cancel the contract.
- An expiry date and presentation period long enough, usually at least 15–21 days after shipment.
- The L/C is subject to UCP 600.
Late payment
Add a late-payment interest clause, for example a set rate for each day of delay. More importantly: the seller has the right to hold the goods and withhold the documents until paid in full, and to sell the goods to someone else if payment is late beyond a deadline, with any costs borne by the buyer.
Don't forget
The deposit should be non-refundable if the buyer cancels unilaterally, to cover the raw materials you've already bought.